A. Purpose. See § DR-905A for details.
B. Basic requirements.
1. This section shall not become effective until approved by the Court pursuant to N.J.A.C. 5:93-8.2.
2. The Township of Medford shall not spend development fees until the Court has approved a plan for spending such fees in conformance with N.J.A.C. 5:93-5.1(c).
 
C. Definitions. See § DR-905C for terms associated with development fees and affordable housing.
D. Residential development fees.
1. Imposed fees.
a. Within all Township zoning district(s), residential developers, except for developers of the types of development specifically exempted below, shall pay a fee of 1.5% of the equalized assessed value for residential development provided no increased density is permitted.

b. When an increase in residential density pursuant to N.J.S.A. 40:55D-70d(5) (known as a density or "d" variance) has been approved, developers shall be required to pay a development fee of 6% of the equalized assessed value for each additional unit that may be realized, except that this provision shall not be applicable to a development that will include a set-aside of affordable housing units. However, if the zoning on a site has changed during the two-year period preceding the filing of such a variance application, the base density for the purposes of calculating the bonus development fee shall be the highest density permitted by right during the two-year period preceding the filing of the variance application.

2. Eligible exactions, ineligible exactions and exemptions for residential development. See § DR-905D.2
 
E. Nonresidential development fees.
1. Imposed fees.
a. Within all zoning districts, nonresidential developers, except for developers of the types of development specifically exempted, shall pay a fee equal to 2.5% of the equalized assessed value of the land and improvements for all new nonresidential construction on an unimproved lot or lots.

b. Nonresidential developers, except for developers of the types of development specifically exempted herein, shall also pay a fee equal to 2.5% of the increase in equalized assessed value resulting from any additions to existing structures to be used for nonresidential purposes.

c. Development fees shall be imposed and collected when an existing structure is demolished and replaced. The development fee of 2.5% shall be calculated on the difference between the equalized assessed value of the preexisting land and improvements and the equalized assessed value of the newly improved structure, i.e., land and improvements, at the time the final certificate of occupancy is issued. If the calculation required under this section results in a negative number, the nonresidential development fee shall be zero.

2. Eligible exactions, ineligible exactions and exemptions for nonresidential development. See § DR-905E.2 for details.

F. Collection procedures.
1. Upon the granting of a preliminary, final or other applicable approval for a development, the applicable approving authority shall direct its staff to notify the construction official responsible for the issuance of a building permit.

2. For nonresidential developments only, the developer shall also be provided with a copy of Form N-RDF "State of New Jersey Non-Residential Development Certification/Exemption" to be completed as per the instructions provided. The developer of a nonresidential development shall complete Form N-RDF as per the instructions provided. The construction official shall verify the information submitted by the nonresidential developer as per the instructions provided in the Form N-RDF. The Tax Assessor shall verify exemptions and prepare estimated and final assessments as per the instructions provided in Form N-RDF.

3. The construction official responsible for the issuance of a building permit shall notify the local Tax Assessor of the issuance of the first building permit for a development which is subject to a development fee.

4. Within 90 days of receipt of that notice, the Municipal Tax Assessor, based on the plans filed, shall provide an estimate of the equalized assessed value of the development.

5. The construction official responsible for the issuance of a final certificate of occupancy shall notify the local Assessor of any and all requests for the scheduling of a final inspection on property which is subject to a development fee.

6. Within 10 business days of a request for the scheduling of a final inspection, the Municipal Assessor shall confirm or modify the previously estimated equalized assessed value of the improvements associated with the development; calculate the development fee; and thereafter notify the developer of the amount of the fee.

7. Should the Township of Medford fail to determine or notify the developer of the amount of the development fee within 10 business days of the request for final inspection, the developer may estimate the amount due and pay that estimated amount consistent with the dispute process set forth in Subsection b of Section 37 of P.L. 2008, c. 46 (N.J.S.A. 40:55D-8.6).

8. Fifty percent of the development fee shall be collected at the time of issuance of the building permit. The remaining portion shall be collected at the issuance of the certificate of occupancy. The developer shall be responsible for paying the difference between the fee calculated at building permit and that determined at issuance of certificate of occupancy.

9. Appeal of development fees:
 
a. A developer may challenge residential development fees imposed by filing a challenge with the County Board of Taxation. Pending a review and determination by the Board, collected fees shall be placed in an interest-bearing escrow account by the Township of Medford. Appeals from a determination of the Board may be made to the tax court in accordance with the provisions of the State Tax Uniform Procedure Law, N.J.S.A. 54:48-1 et seq., within 90 days after the date of such determination. Interest earned on amounts escrowed shall be credited to the prevailing party.

b. A developer may challenge nonresidential development fees imposed by filing a challenge with the Director of the Division of Taxation. Pending a review and determination by the Director, which shall be made within 45 days of receipt of the challenge, collected fees shall be placed in an interest-bearing escrow account by the Township of Medford. Appeals from a determination of the Director may be made to the tax court in accordance with the provisions of the State Tax Uniform Procedure Law, N.J.S.A. 54:48-1 et seq., within 90 days after the date of such determination. Interest earned on amounts escrowed shall be credited to the prevailing party.

G. Affordable Housing Trust Fund. See § DR-905G for detailed information.
H. Use of funds. See § DR-905H for details.

I. Monitoring. On or about May 10 of each year through 2025, the Township of Medford shall provide reporting of trust fund activity to the DCA, Local Government Services (LGS), or other entity designated by the State of New Jersey, with a copy provided to the Fair Share Housing Center and posted on the municipal website, using forms developed for this purpose by the DCA, COAH, or LGS. This reporting shall include an accounting of all housing trust fund activity, including the collection of development fees from residential and nonresidential developers, payments in lieu of constructing affordable units on site, funds from the sale of units with extinguished controls, barrier-free escrow funds, rental income, repayments from affordable housing program loans, and any other funds collected in connection with the Township of Medford's housing program, as well as in connection with the expenditure of revenues and implementation of the plan approved by the Court.

J. Ongoing collection of fees.
1. The ability for the Township of Medford to impose, collect and expend development fees shall expire with the end of the repose period covered by its judgment of compliance unless the Township of Medford has filed an adopted Housing Element and Fair Share Plan with the Court or with a designated administrative entity of the State of New Jersey, has petitioned for a judgment of compliance or substantive certification, and has received approval of its development fee ordinance by the entity that will be reviewing the Housing Element and Fair Share Plan.

2. If the Township of Medford fails to renew its ability to impose and collect development fees prior to the expiration of its judgment of compliance, it may be subject to forfeiture of any or all funds remaining within its municipal trust fund. Any funds so forfeited shall be deposited into the New Jersey Affordable Housing Trust Fund established pursuant to Section 20 of P.L. 1985, c. 222 (N.J.S.A. 52:27D-320). The Township of Medford shall not impose a development fee on a development that receives preliminary or final site plan approval after the expiration of its judgment of compliance and repose, nor shall the Township of Medford retroactively impose a development fee on such a development. The Township of Medford shall not expend any development fees after the expiration of its judgment of compliance.